Breach of contract

From Wikipedia, the free encyclopedia

Breach of contract is a legal cause of action and a type of civil wrong, in which a binding agreement or bargained-for exchange is not honored by one or more of the parties to the contract by non-performance or interference with the other party's performance. Breach occurs when a party to a contract fails to fulfill its obligation(s), whether partially or wholly, as described in the contract, or communicates an intent to fail the obligation or otherwise appears not to be able to perform its obligation under the contract. Where there is breach of contract, the resulting damages have to be paid to the aggrieved party by the party breaching the contract.

If a contract is rescinded, parties are legally allowed to undo the work unless doing so would directly charge the other party at that exact time.

What constitutes a breach of contract[edit]

There exists two elementary forms of breach of contract.

The first is actual failure to perform the contract as and when specified constitutes the first and most obvious type of breach. A contract lays down what must be done, what cannot be done, and when it must be done. If what was prescribed has not been done within the stipulated or reasonable period, there has been a breach of contract.

A further form of breach of contract is conduct indicating an unwillingness or inability to perform an obligation arising from that contract.

As noted by Seddon et al, these forms of breach of contract overlap, and an actual failure to perform may manifest an unwillingness or inability to perform.[1] This is not always the case: an individual may fail to perform a contractual obligation even when willing or able.

These classifications describe only how a contract can be breached, not how serious the breach is. A judge will make a decision on whether a contract was breached based on the claims of both parties.[2]

The first type above is an actual breach of contract. The two other types are breaches as to the future performance of the contract and are technically known as renunciatory breaches. The defaulting party renunciates the contract in advance of when it is required to performs its obligations. Renunciatory breach is more commonly known as "anticipatory breach."

Classifications of breaches of contract[edit]

The general law has three categories of breaches of contract, which measure of the seriousness of the breach. In the absence of a contractual or statutory provision, any breach of contract is categorized:[3]

  • breach of warranty;
  • breach of condition; or
  • breach of an innominate term, otherwise known as an intermediate term.

There is no "internal rating system" within each of these categories (such as "a serious breach of warranty"). Any breach of contract is of a breach of warranty, condition or innominate term.

In terms of priority of classification of these terms, a term of a contract is an innominate term unless it is clear that it is intended to be a condition or a warranty.

Case law[edit]

England[edit]

New Zealand[edit]

Rights to damages for breach[edit]

Any breach of contract (warranty, condition or innominate term) gives rise to a right in the hands of the innocent party to recover their damage suffered which caused by the breach of contract by the defaulting party. Damages in the UK are the only[4] remedy available for breach of a warranty.[citation needed] Those damages can come in different forms such as an award of monetary damages, liquidation damages, specific performances, rescission, and restitution.[5]

Damages are classified as being compensatory or punitive. Compensatory damages are rewarded in an attempt to make place the innocent party in the position that would have been occupied "but for" the breach.[6] Those damages are most often awarded as payments. Punitive damages are given to "punish or make an example of a wrongdoer who has acted willfully, maliciously or fraudulently".[7] Punitive damages are awarded only in extreme cases and usually along with compensatory damages.

Damages for disappointment[edit]

Damages for distress or disappointment are not generally allowed by the courts, but cases where the award of such damages has been considered and agreed include Jarvis v Swans Tours Ltd (1972) and Farley v Skinner (2001).

Right to terminate for breach[edit]

A right to terminate a contract arises for:

  1. breach of a condition of the contract, no matter how trivial the breach of the condition may be;
  2. repudiatory breach, that is an actual breach of an innominate term, where the consequence of the breach is sufficiently serious to give rise to a right to terminate; or
  3. renunciatory breach (aka anticipatory breach), where the other party makes clear to the innocent party that it:
    1. is not going to perform the contract at all, or
    2. is going to commit a breach of a condition, or
    3. is going to commit a breach of an innominate term,
and the consequences will be such as to entitle the innocent party to treat the contract as at an end.

An innocent party is therefore entitled to elect to terminate a contract only for breach of a condition of the contract, repudiatory breach or renunciatory breach.

To terminate a contract for repudiatory breach, the innocent party must tell the defaulting party. Many commercial contracts include clauses that set out a process whereby notice must be given and in what form. Consequently, if there is a written contract, care should be taken to check the contract terms and to ensure compliance notwithstanding that the other party may, on the face of it, have committed a clear and repudiatory breach. It is only when the defaulting party is told that a repudiatory breach has been "accepted" that the contract is terminated. If the defaulting party is not told the repudiatory breach has been accepted, the contract continues in force. An innocent party is not compelled to exercise its right to terminate, and accept a repudiatory breach. Otherwise, the contract continues in force.[8]

Repudiatory breaches[edit]

Conduct is repudiatory if it deprives the innocent party of substantially the whole of the benefit intended to be received as consideration for performance of its future obligations under the contract. Different forms of words are used by courts to express this central concept. The most prominent is whether the breach goes to the root of the contract. Those forms of words are simply different ways of expressing the "substantially the whole benefit" test.[9]

Sometimes the innocent party may be deprived of its entitlement to damages for repudiatory breach of contract:

  • if the innocent party is irremediably disabled from performance, provided that that inability to perform on the part of the innocent party is not itself attributable to the repudiatory breach;[10]
  • if the innocent party has a settled intention not to perform.[11]

Renunciatory breaches[edit]

Conduct is renunciatory if it shows an intention to commit a repudiatory breach. The conduct would lead a reasonable person to conclude that the party does not intend to perform its future obligations when they fall due.[12]

Showing an intention to perform a contract in a manner which is inconsistent with the terms of the contract also shows an intention not to perform the contract.[13] Whether such conduct is so severe so as to amount to a renunciatory breached depends upon whether the threatened difference in performance is repudiatory. An intention to perform connotes a willingness to perform, but willingness in this context does not mean a desire to perform despite an inability to do so. To say "I would like to but I cannot" negatives intent just as much as "I will not".[12] Contracting parties must perform contracts in strict accordance with their terms: what was agreed in the first instance when the contract was formed. To do otherwise is therefore a breach of contract.

In the event of a renunciatory breach, the innocent party may:

  • choose to accept the breach at once and to terminate the contract, without waiting for the due date of performance, or
  • wait for the time for performance of the contract.

If the defaulting party does not perform when the time for performance arrives, the contract may be terminated. However, if the defaulting party performs, the right to terminate is lost forever.

Conduct comprising a breach for performance of contractual obligations that have fallen due may be insufficient to be a repudiation. However:

  • Nevertheless, conduct may be a renunciation because it would lead the reasonable observer to conclude that there was an intention not to perform in the future, and
  • the past and threatened future breaches taken together would be repudiatory.

The reason for a defaulting party committing an actual breach is generally irrelevant to whether it constitutes a breach, or whether the breach is a repudiation (this is an incident of strict liability for the performance of contractual obligations). However, the reason may be highly relevant to what such breach would lead the reasonable observer to conclude about the defaulting party's intentions in relation to future performance and therefore to the issue of renunciation. Often, the question whether conduct is a renunciation falls to be judged by reference to the defaulting party's intention, which is objectively evinced by past breaches and other words and conduct.

Breach of warranty[edit]

A breach of a warranty of a contract creates a right to damages for the loss suffered, which was caused by the breach. These "minor" breaches do not entitle the innocent party to terminate the contract. The innocent party cannot sue the party in default for specific performance: only damages. Injunctions (specific performance is a type of injunction) to restrain further breach of a warranty are likely to be refused on the basis that (1) injunctions are a discretionary remedy, and (2) damages are an adequate remedy in the circumstances of the case.

Suppose a homeowner hires a contractor to install new plumbing and insists that the pipes, which will ultimately be hidden behind the walls, must be red. The contractor instead uses blue pipes that function just as well. Although the contractor breached the literal terms of the contract, the homeowner cannot ask a court to order the contractor to replace the blue pipes with red pipes. The homeowner can only recover the amount of his or her actual damages. In this instance, this is the difference in value between red pipe and blue pipe. Since the color of a pipe does not affect its function, the difference in value is zero. Therefore, no damages have been incurred and the homeowner would receive nothing (see Jacob & Youngs v. Kent.)

However, had the pipe color been specified in the agreement as a condition, a breach of that condition may well constitute a "major"—i.e. a repudiatory breach. Simply because a term in a contract is stated by the parties to be a condition does not necessarily make it so. Such statements though are one of the factors taken into account to decide whether it is a condition or warranty of the contract. Other than where the colour of the pipes went to the root of the contract (suppose the pipes were to be used in a room dedicated to artwork related to plumbing, or dedicated to high fashion), it would more than likely be a warranty, not a condition.

The general rule is that stipulations as to time in a contract are not conditions of the contract (there are exceptions, such as in shipping contracts; it depends in part upon the commercial importance of timely delivery in all the circumstances of the case). As such, missing a date for performance stipulated in a contract is usually a breach of warranty. However, when a contract specifies time is of the essence or otherwise contains an express or implied term that times for performance are critical, stipulations as to time will be conditions of the contract. Accordingly, if a party fails to meet a meet the time stipulations, it will be a breach of a condition of the contract, entitling the innocent party to terminate.

Breach of a condition[edit]

Breach of a condition of a contract is known as a repudiatory breach. Again, a repudiatory breach entitles the innocent party at common law to (1) terminate the contract, and (2) claim damages. No other type of breach except a repudiatory breach is sufficiently serious to permit the innocent party to terminate the contract for breach.

Types of breach[edit]

Contracts often use wording other than repudiatory breach to describe a type of breach of contract. These contractual terms include material breach, fundamental breach, substantial breach, serious breach. These alternative wordings have no fixed meaning in law but are interpreted within the context of the contract that they are used. For that reason, the meaning of the different terms varies from case to case. Possible interpretations of their meaning include "repudiatory breach", and "serious breach, but not as serious as a repudiatory breach".

Trivial breach[edit]

A trivial breach is one that does not meet the standard for designation as a material, serious or substantial breach.

An Arizona Supreme Court decision in a 1990 commercial retail lease case noted that "the overwhelming majority of [US] jurisdictions... hold the landlord's right to terminate is not unlimited. We believe a court's decision to permit termination must be tempered by notions of equity and common sense. We thus hold a forfeiture for a trivial or immaterial breach of a commercial lease should not be enforced."[14]

In Rice (t/a The Garden Guardian) v Great Yarmouth Borough Council (2000),[15] the UK Court of Appeal decided that a clause which provided that the contract could be terminated "if the contractor commits a breach of any of its obligations under the contract" should not be given its literal meaning: it was considered "contrary to business common sense" to allow any breach at all, however trivial, to create grounds for termination.[16]

Material breach[edit]

A material breach has been held to mean "a breach of contract which is more than trivial, but need not be repudiatory" and confirmed as meaning "a breach which is substantial. The breach must be a serious matter, rather than a matter of little consequence."[17] A breach of contract will likely constitute a material breach if the term of the contract which has been breached is a condition of the contract. A variety of tests may be applied to terms of contracts to decide whether a term is a warranty or a condition of the contract.

In respect to the EPC Agreements,[clarification needed] material breach is defined as "shall mean a breach by either Party of any of its obligations under this Agreement which has or is likely to have a Material Adverse Effect on the Project and which such Party shall have failed to cure".[citation needed]

Other UK cases which relate to the concept of a material breach include:

  • National Power plc v United Gas Company Ltd. (1998),[18] where Colman J considered wording relating to "a material breach of any of [the guilty party's] obligations", allowing termination of the contract if remedy of such breach had not been commenced within seven days. The judge ruled that recognition that a material breach might be remedied distinguished the concept from a repudiatory breach, and there was no commercial sense in a clause restricting the common law rights of the innocent party, in relation to a repudiatory breach, and therefore "material breach" must refer to a form of breach which is not repudiatory.[16]
  • Glolite Ltd. v Jasper Conran Ltd. (1998), where Neuberger J stated that

    Whether a breach of an agreement is "material" must depend upon all the facts of the particular case, including the terms and duration of the agreement in question, the nature of the breach, and the consequences of the breach.[19]

    and that

    when judging what the parties meant when they referred to a breach having to be "material" and "remediable" (sic) it seems to me that they must have had in mind, at least to some extent, the commercial consequences of the breach.[19]

  • Phoenix Media Limited v Cobweb Information (2000) [20]
  • Dalkia Utilities Services plc v Celtech International (2006) noted that assessing "materiality" involved looking at the actual breaches, their consequences, [the guilty party's] explanation for the breaches, their context within the agreement, the consequences of holding the agreement determined and the consequences of allowing the agreement to continue.[21] Financial difficulties experienced by Celtech meant that they missed three payments out of 174 due over the 15 year life of the contract. These represented 8.5% of the total contract sum and were therefore not trivial or minimal, but Celtech were making attempts to pay and therefore not in repudiatory breach. Celtech were, however, in material breach of the contract and the contractual right to terminate could therefore be exercised by Dalkia.[16]
  • Gallaher International Ltd v Tlias Enterprises (2008) [22]
  • Crosstown Music Company v Rive Droite Music Ltd (2009), also making the point that a "material" breach was more significant than a "trivial" breach.[23] Mann J referred to the Dalkia and Gallaher cases in his speech.[23]: para. 98 

Right to remedy a breach[edit]

A party in breach of contract may have the right to remedy their breach, for example if the breach itself is remediable and a provision for remedy or a time period for exercising such as right is included within the contract. In the case of Vinergy International (PVT) Ltd v Richmond Mercantile Limited FZC (2016), a clause within the contract between the disputing parties stated that "failure ... to observe any of the terms herein and to remedy the same where it is capable of being remedied within the period specified in the notice given by the aggrieved party to the party in default, calling for remedy, being a period not less than twenty (20) days" would constitute grounds for termination of the contract.[24] The period allowed for such a remedy may be referred to as a "cure period".[25] A right to make use of a cure period may not be available where the innocent party chooses to accept a repudiatory breach and therefore exercise its common law rather than its contractual rights.[25]

Fundamental breach[edit]

Fundamental breach of contract is no longer the test for a serious breach of contract to justify termination. The test is that set out for repudiatory breach, above. The concept of fundamental breach as a free standing legal concept no longer has any legal force[26] but is now simply another possible term of a contract that needs to be construed like any other term of a contract.

A fundamental breach is usually read as a reference to a repudiatory breach.[27]

A term may be a condition in Australian law if it satisfies one test known as the test of essentiality.[28] The test of essentiality requires that the promise (term) was of such importance to the promisee that he or she would not have entered into the contract without the assurance of strict or substantial performance of the promise, and that ought to have been apparent to the promisor. This is an objective test of the parties' intention at the time of formation of the contract.

If the contractor in the above example had been instructed to use copper pipes but instead used iron pipes that would not last as long as the copper pipes would have lasted, the homeowner can recover the cost of actually correcting the breach by taking out the iron pipes and replacing them with copper pipes.

There are exceptions. Legal scholars and courts have been known to find that the owner of a house whose pipes are not the specified grade or quality (a typical hypothetical example) cannot recover the cost of replacing the pipes for the following reasons:

  1. Economic waste. The law does not favor tearing down or destroying something that is valuable (almost anything with value is "valuable"). In this case, significant destruction of the house would be required to completely replace the pipes and so the law is hesitant to enforce damages of that nature. See Peevyhouse v. Garland Coal & Mining Co..
  2. Pricing in. In most cases of breach, a party to the contract simply fails to perform one or more terms. In those cases, the breaching party should have already considered the cost to perform those terms and thus "keeps" that cost when it does not perform. That party should not be entitled to keep those savings. However, in the pipe example, the contractor never considered the cost of tearing down a house to fix the pipes and so to expect it to pay damages of that nature is unreasonable.[citation needed]

Most homeowners would be unable to collect damages that compensate them for replacing the pipes but would be awarded damages that compensate them for the loss of value in the house. For example, if the house is worth $125,000 with copper and $120,000 with iron pipes, the homeowner would be able to collect the $5,000 difference and nothing more.

In the United States, the Restatement (Second) of Contracts lists the following criteria to determine whether a specific failure constitutes a material breach:[29]

In determining whether a failure to render or to offer performance is material, the following circumstances are significant:

(a) the extent to which the injured party will be deprived of the benefit which he reasonably expected;
(b) the extent to which the injured party can be adequately compensated for the part of that benefit of which he will be deprived;
(c) the extent to which the party failing to perform or to offer to perform will suffer forfeiture;
(d) the likelihood that the party failing to perform or to offer to perform will cure his failure, taking account of all the circumstances including any reasonable assurances;
(e) the extent to which the behavior of the party failing to perform or to offer to perform comports with standards of good faith and fair dealing.

Anticipatory breach[edit]

Renunciatory breach (usually referred to as anticipatory breach or breach by anticipatory repudiation) is an unequivocal indication that the party will not perform when performance falls due or a situation in which future non-performance is inevitable. An anticipatory breach gives the innocent party the option to terminate the contract immediately and sue for damages or to wait for the time of performance. If the party required to perform does not do so when it is required by the contract, the innocent party can terminate then.[30][31]

For example, A contracts with B on January 1 to sell 500 quintals of wheat and to deliver it on May 1. Subsequently, on April 15, A writes to B and says that he will not deliver the wheat. B may immediately consider the breach to have occurred and file a suit for damages for the scheduled performance even though A has until May 1 to perform. However, a unique feature of anticipatory breach is that if an aggrieved party chooses not to accept a repudiation occurring before the time set for performance, the contract continues on foot, but also there will be no right to damages unless an actual breach occurs.[32]

See also[edit]

References[edit]

  1. ^ Seddon (2012).
  2. ^ "Breach of Contract — Judicial Education Center". jec.unm.edu. Retrieved 10 April 2020.
  3. ^ "Grand China Logistics Holding (Group) Co. Ltd v Spar Shipping AS (Rev 1) [2016] EWCA Civ 982". Retrieved 7 February 2019.
  4. ^ Grand China, paragraph 98
  5. ^ "What Are the Remedies Available for a Contract Breach?". Brown & Charbonneau, LLP. 5 September 2019. Retrieved 10 April 2020.
  6. ^ "Breaches of Contract - The Basics :: Litigant". www.litigant.com.au. Retrieved 23 August 2020.
  7. ^ "Remedies for Breach of Contract — Judicial Education Center". jec.unm.edu. Retrieved 10 April 2020.
  8. ^ "Breach of Contract Claims".
  9. ^ "Federal Commerce & Navigation Co Ltd v Molena Alpha Inc (The Nanfri) [1979] AC 757 per Lord Wilberforce".
  10. ^ Cases such as Braithwaite v Foreign Hardwood Company (1905) 2KB 543, British and Beningtons Ltd v North Western Cachar Tea Co (1923) AC 48, and Cooper, Ewing & Co Ltd v Hamel & Horley Ltd (1923) 13 Ll L Rep 590, discussed in England and Wales Court of Appeal (Civil Division), Acre 1127 Ltd. (In Liquidation) v De Montfort Fine Art Ltd. (2011) EWCA Civ 87 (9 February 2011), accessed 13 June 2021
  11. ^ Pease, C. and Riach, C., A clearer picture of entitlement to damages flowing from repudiatory breach?, Legal Briefing, published May 2011, accessed 13 June 2021
  12. ^ a b "Universal Cargo Carriers Corporation v Citati [1957] 2 QB 401".
  13. ^ "Ross T Smyth & Co Ltd v T.D. Bailey, Son & Co [1940] 3 All ER 60".
  14. ^ Supreme Court of Arizona, Foundation Dev. Corp. v. Loehmann's, 163 Ariz. 438 (1990), accessed 25 January 2021
  15. ^ All ER (D) 902, CA
  16. ^ a b c Winser, C., Terminating a Commercial Contract for Material Breach, Crown Office Chambers, June 2007
  17. ^ Jackson LJ, in England and Wales Court of Appeal (Civil Division), Mid Essex Hospital Services NHS Trust v Compass Group UK and Ireland Ltd (t/a Medirest) (2013), EWCA Civ 200, paragraph 126.
  18. ^ All ER(D) 321
  19. ^ a b Quoted by Clarke J in England and Wales High Court (Commercial Court), Dalkia Utilities Services Plc v Celtech International Ltd (2006), EWHC 63 (Comm) (27 January 2006)
  20. ^ Unreported, 16 May 2000
  21. ^ 1 Lloyds Rep 599
  22. ^ England and Wales High Court (Commercial Court), Gallaher International Ltd v Tlais Enterprises Ltd (Rev 1) (2008), EWHC 804 (Comm) (18 April 2008), accessed 15 June 2021
  23. ^ a b England and Wales High Court (Chancery Division), Crosstown Music Company 1, Llc v Rive Droite Music Ltd & Ors (2009), EWHC 600 (Ch) (25 March 2009), accessed 15 June 2021
  24. ^ England and Wales High Court (Commercial Court), Vinergy International (PVT) Ltd v Richmond Mercantile Limited FZC, [2016] EWHC 525 (Comm) (15 March 2016), accessed 2 January 2022, paragraph 11 (clause 17 within the contract)
  25. ^ a b Upadhyaya, N., Termination for repudiatory breach: do contractual notification provisions apply?, Allen & Overy, published 17 May 2016, accessed 2 January 2022
  26. ^ Photo Production Ltd v Securicor Transport Ltd [1980] AC 827, per Lord Wilberforce at p. 843; Lord Reid in Suisse Atlantique [1967] 1 AC 361 at 406
  27. ^ Suisse Atlantique, Ibid
  28. ^ Tramways Advertising Pty Ltd v Luna Park [1938] NSWStRp 37, (1938) 38 SR (NSW) 632, Supreme Court (NSW, Australia).
  29. ^ American Law Institute, Restatement (Second) of Contracts § 241 (1981)
  30. ^ Progressive Mailing House v Tabali Pty Ltd [1985] HCA 14, (1985) 157 CLR 17 at p. 48, High Court (Australia)
  31. ^ Foran v Wight [1989] HCA 51, (1989) 168 CLR 385 at pp 416, 441-2, High Court (Australia).
  32. ^ Paterson, Jeannie; Robertson, Andrew; Duke, Arlen (2012). Principles of Contract Law (Fourth ed.). Sydney: Thomson Reuters (Professional) Australia Limited. p. 440.

Bibliography[edit]

Academic literature